PROCESS INSTRUCTIONS FOR PARTITION WALL

90 minutes 1 x 12 mm

Partition wall up against pine rail or steel C profile (both sides)

  • Material
  • On both sides 1 x 12 mm Permoxxboard
  • Handling
  • Strips 100 mm both sides screwed on construction U and C profiles, C-C 100 mm, 75 mm rock wool (45kg/m3) with corresponding C-100 en U-100 profile 0,60 mm C-C 600 mm.
  • Seams
  • Seams 2 – 4 mm must always be glued with fire-resistant sealant.
  • Edges
  • When applicable fill up the edges with strip of rock wool.
  • Fire-resistance:
    Efectis Raport:
  • 2012-Efectis-R0091
  • img
  • Test reports
    For fully detailed construction always consult the construction in the certificate
  • Noise deadning:
    Ingenieurs Red: 20120122-01
  • Cauberg-Huygen

 